Project type: Internal plastering and surface finishing
Area: 160 m²
Тривалість: 3 days
Передісторія:
Нові гіпсокартонні плити
Scope of Work:
Supply and delivery of all materials
Plastering over newly installed plasterboards
Straightening and preparing all surfaces
Installation of angle and stop beads for precision corners
Application of fibre mesh tape to reinforce joints and prevent cracking
Two-coat skim finish applied to walls and ceilings
Complete tidy-up after works
Result:
This 3-day loft plastering project was completed for one of our regular clients. The work required meticulous attention to detail due to numerous small angles and corners. The MAC Plastering Team delivered a perfectly smooth and durable finish, with all surfaces precisely levelled and ready for decoration.